Revitalizing an iconic Toronto landmark, The Ryerson Athletics Centre at the Gardens will create a legacy for a new generation of Ryerson students and the local community and a new exciting home for the Ryerson Rams. Nearly 220,000 sq ft (20,400 m2) on the building's upper floors will supplement the university's existing athletic facilities. The new centre's street-level retail complex will include a flagship grocery store owned by project partner Loblaw Companies Limited, as well as two Loblaw retail tenants.
DATES
START
December 2009
PROJECTED COMPLETION
Winter 2012
PROJECTED OCCUPANCY
Winter 2012
PROJECT TEAM
PROJECT TEAM
ARCHITECTS
Base building: Turner Fleischer Architects Inc. Ryerson fit up: BBB Architects Inc.
CONTRACTOR
HERITAGE CONSULTANT
SIGNAGE CONSULTANT
PROJECT MANAGER
STATUS
: May 2012
All Levels
AV, communications and security systems distribution work is ongoing throughout the facility.
Level 1 – Lobby
Installation of the main feature stair structure is complete, and all of the scaffolding in the lobby has been removed. Work on the floor and wall finishes has begun.
Level 2 – Athletic Centre and Reception Area
Laying down and grinding of the terrazzo floor topping is complete, extending from the gym to the café and reception area. Millwork design for the Café is complete, and will be under production shortly. The turnstile system bases for the entrance to the fitness centre have been installed and installation of the sheet goods (a type of rubber flooring) is underway throughout the 2nd floor. Acoustic fibre and related ceiling work is ongoing in the gym (the acoustic treatment will make it easier to hear in the large space), and both the powered and manually operated basketball backstops have been installed. The basketball floor assembly is due to begin shortly.
Level 3 – Ice Rink
Installation of the seating for the arena is 95% complete. Installation of the glass panel system above the dasher boards (the white boards around the rink that support the glass panels) is also complete. The ice-making system is being commissioned. General cleaning of the entire arena and dome is also underway. Office areas and related rooms are being prepared to accept the ceiling systems and lighting.
Level 4 – Mechanical Rooms and Concession Stands
Concrete floors on the East and West concourses have been ground and polished. Installation of glass guard rails is nearing completion. Lighting systems for the arena are complete and have been turned on. Concession counters and roll-down grilles will be installed shortly.
FACILITIES
- Total Space: 222,970 sq ft (20,714 m2)
- NHL sized ice rink, seating for 2,796
- Multi-purpose court, 1,000+ seats
- Fitness centre, studios and high-performance gym
- Ryerson Rams athletics store
- Café/Juice Bar
- Facilities will be made accessible to the community
Retail:
- Loblaws food store (70,000 sq ft / 6,500 m2) at street level
- Two Loblaw tenants on the second floor
- Underground parking for Loblaw customers
Budget and Financing
Budget Phase 1
$60 million
Financing
$20 million Infrastructure Canada
$20 million Student levy
$20 million Fundraising
Budget Phase 2 - Expansion
$17.5 million
Financing
$12.5 million Internal Sources